Lithium South Development Corporation: Preliminary Economic Assessment Filed on SEDAR


VANCOUVER, British Columbia, April 30, 2024 /PRNewswire/ -- Lithium South Development Corporation (the "Company" or "Lithium South") (TSX-V: LIS) (OTCQB: LISMF) (Frankfurt: OGPQ) is pleased to announce it has today filed on SEDAR plus, its Preliminary Economic Assessment ("PEA report') following the summary results previously announced March 03, 2024. The report titled, N.I. 43-101 Preliminary Economic Assessment Hombre Muerto North Lithium Project, Salta, Argentina, was completed by Knight Piesold Consulting and JDS Energy and Mining Inc., both industry leading independent engineering consulting firms.

The PEA Report provides support for Lithium South to proceed with development plans for a 15,600 tonnes per year lithium carbonate plant, located at its wholly owned, Hombre Muerto North Lithium Project ("HMN Li Project") in Salta, Argentina. The extraction and recovery process for the project is based on conventional solar evaporation of the well brine, magnesium removal with slaked lime and lithium carbonate precipitation using soda ash, which is an industrial proven method of lithium production.

The financial model shows a Net Present Value after tax of US$938 million, an after-tax Internal Rate of Return of 31.6%, and a 2.5-year payback.

Company Founder President and CEO, Adrian F. C. Hobkirk is quoted, "We are very pleased to have achieved this important milestone for the HMN Li Project. The robust economics and room for expansion indicate a promising future for Lithium South."

About Lithium South

Lithium South owns 100% of the HMN Li Project located in Salta and Catamarca Provinces, Argentina, in the heart of the lithium triangle.  The Salar del Hombre Muerto has a history of lithium production, with Arcadium Lithium (as a result of the Alkem and Livent merger) in operation for over twenty-five years, in an area just south of the HMN Li Project. The HMN Li Project is surrounded by a US$4 billion lithium development under construction by POSCO (Korea) and the Sal de Vida Project under development by Arcadium. Exploration work to date has delineated a National Instrument 43-101 compliant 1,583,200 tonne Lithium Carbonate Equivalent ("LCE") Resource (Note 1) on the Alba Sabrina, Natalia Maria, and Tramo claim blocks, three of five non-contiguous blocks that make up the HMN Lithium Project.  With pumping well installation underway, Lithium South is transitioning from being a lithium explorer to becoming a lithium developer.

Qualified Person Statements

Peter Ehren is an independent Lithium Consultant. He has more than two decades of experience in the industry. He started his interest in the lithium business during his master's thesis at Technical University of the Delft where he investigated for BHP Minerals the recovery of lithium from geothermal brine (Salton Sea), applying a Direct Lithium Extraction ("DLE") technology. After his thesis he worked for SQM as a process engineer and R&D manager till 2007. Since 2007 he started to work as independent consultant in the lithium, boron and potassium industry. He is a world expert in solar evaporation systems, phase chemistry and process developments. Additionally, his experience covers product applications, OPEX and CAPEX estimation, process simulations, engineering, R&D and product development.  He has worked in lithium basins and production facilities worldwide.  He is a Chartered Professional (AusIMM) and QP for NI 43-101 and JORC.

Dr. Mark King, Ph.D., F.G.C., P.Geo., of Groundwater Insight, Inc., is the QP for resource estimation components of the PEA., as such term is defined by NI 43-101. Dr. King has extensive experience in salar environments and has been a QP on numerous lithium brine projects, ranging from early exploration to production. Dr. King is independent from the Company and has reviewed and approved the technical information mentioned in this press release.

Richard Goodwin, P.Eng., Project Manager for JDS Energy and Mining, Inc., is independent of Lithium South and a QP as defined under Canadian National Instrument 43-101. Mr. Goodwin is a mining engineer and study manager with over 30 years of experience managing mining operation and projects in various commodities such as base metals, precious metals, PGMs, and diamonds in various domestic and international locations. Mr. Goodwin is responsible for the PEA results, participated directly in the production of this press release, and directly related information in this press release, and approves of the technical and scientific disclosure contained herein.

On behalf of the Board of Directors

Adrian F. C. Hobkirk
President and Chief Executive Officer
Investors / Shareholders call 855-415-8100 / website: lithiumsouth.com 

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. The TSX Venture Exchange has not reviewed the content of this news release and therefore does not accept responsibility or liability for the adequacy or accuracy of the contents of this news release.

Note 1: A report titled, Updated Mineral Resource Estimate ? Hombre Muerto North Project, NI 43-101 Technical Report Catamarca and Salta, Argentina, Mark King, PhD, PGeo, Peter Ehren, M.Sc, MAusIMM, September 5th, 2023.

This news release contains certain "forward-looking statements" within the meaning of Section 21E of the United States Securities and Exchange Act of 1934, as amended. Except for statements of historical fact relating to the Company, certain information contained herein constitute forward-looking statements. Forward-looking statements are based upon opinions and estimates of management at the date the statements are made and are subject to a variety of risks and uncertainties and other factors which could cause actual results to differ materially from those projected in the forward-looking statements. The reader is cautioned not to place undue reliance on forward- looking statements. We seek safe harbor.

Image - https://mma.prnewswire.com/media/2400878/Summary_of_Economic_Results.jpg

SOURCE Lithium South Development Corporation


These press releases may also interest you

at 20:00
Labrador Iron Ore Royalty Corporation (the "Corporation") announced the results of the election of directors at its annual and special meeting of holders of common shares held today by way of a hybrid meeting conducted virtually and in person. The...

at 19:35
Silver Viper Minerals Corp. (the "Company" or "Silver Viper") announces that it has closed the final tranche (the "Final Tranche") of its non-brokered private placement financing (the "Offering") pursuant to the Listed Issuer Financing Exemption...

at 19:28
BTQ Technologies Corp. (the "Company") (CBOE CA: BTQ) is providing this bi-weekly update on the status of the management cease trade order issued on April 3, 2024 (the "MCTO"), by its principal regulator, the British Columbia Securities Commission...

at 19:02
SPC Nickel Corp. ("SPC Nickel" or the "Company") is pleased to announce an upsize of its previously announced non-brokered private placement (the "Offering") of common share units ("Common Share Units") and flow?through common shares ("FT Shares"). ...

at 18:35
Star Diamond Corporation ("Star Diamond" or the "Corporation") is pleased to announce that all of the nominees listed in the management proxy circular dated April 1, 2024 were elected as directors of the Corporation at its annual meeting of...

at 18:10
DMG Blockchain Solutions Inc. ("DMG" or the "Company"), a vertically integrated blockchain and data center technology company, today announces it will release financial results for its second quarter 2024 ending March 31, 2024 on Wednesday, May...



News published on and distributed by: