Planning of major works for 2024 and recap of the deconstruction of the Original Champlain Bridge


MONTRÉAL, April 11, 2024 /CNW/ - Today, The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) presented the work that it will carry out in 2024 on the infrastructure under its responsibility. In the coming months, work will be performed on the Jacques Cartier Bridge, the federal sections of the Bonaventure Expressway and the Honoré Mercier Bridge. At this media briefing, JCCBI also provided a recap of the deconstruction of the original Champlain Bridge.

Bonaventure Expressway

Maintenance work to repair slabs will be carried out on the section of elevated lanes between the Victoria Bridge and the Peel Basin. These activities will require reconfiguring and reducing the number of lanes to two per direction from May to November inclusively. They will also involve complete and partial closures to the expressway and on-ramps at night and on weekends.

Work will also be carried out in the Clément Bridge sector to repair bridge girders and the concrete surfaces of the approach lanes. Several important hindrances are to be expected in this sector. To uphold worker safety, the speed limit will be set at 50 km/h over the entire Bonaventure corridor from June to November inclusively.

Honoré Mercier Bridge 

Pier repairs and the cleaning and painting of steel components will also be done in 2024 and will require some night-time closures of the on-ramps and off-ramps on the South Shore side.

Jacques Cartier Bridge

Since February 2024, the cleaning and painting of steel components have had a partial impact on some illumination sections and have required the complete closure of the sidewalk between the Île Sainte-Hélène pavilion and Montréal until the end of November. However, pedestrians can use the multipurpose path during this period.

As part of the plans to maintain the bridge's service life beyond 150 years, renovations will also be done to the Île Sainte-Hélène pavilion that involve the building envelope, Jacques Cartier bust, windows, mosaic tiling, and pavilion interior. The goal is to extend the life of the pavilion. 

This fall, demolition work on the former toll station will take place on the Longueuil side.

Deconstruction following sustainable development principles

JCCBI achieved its goal to successfully deconstruct the historic former Champlain Bridge through in-depth planning to minimize the impact on the environment and the community, and recycle or reuse most of the structure's materials. Overall, 56 spans, 53 piers and 53 pier footings were deconstructed by Nouvel Horizon Saint-Laurent G.P. (NHSL), a consortium made up of Pomerleau Inc. and Delsan-A.I.M. Environmental Services Inc. This project was completed two months ahead of schedule and within the initial budget of $225.7 million, plus direct costs related to COVID-19 management. Only three complaints were recorded during the 41 months of work.

Here are some other key aspects of the project:

"Given the scale of the historic deconstruction of the original Champlain Bridge, JCCBI adopted a bold approach to go above and beyond with this project.  Although we knew the bridge had to be taken down, we still wanted to leave the community with several tangible gifts. This multifaceted project included environmental protection, material reuse, research, commemorative initiatives, and the redevelopment of public spaces to benefit the community. I firmly believe that we carried out this major project with exemplary respect for the environment and the community," said Sandra Martel, Engineer and CEO, JCCBI. "I am extremely proud of this result, which came about through meticulous preparation, constant communication, and close collaboration between JCCBI's teams, the consultants, and our contractor NHSL. I sincerely thank everyone for their contribution," she concluded.

For more details on this work and the deconstruction project:

About JCCBI

As a manager of important infrastructure, The Jacques Cartier and Champlain Bridges Incorporated is a Crown corporation established in 1978 that is responsible for the Jacques Cartier Bridge, the original Champlain Bridge, the Estacade, the Île des Soeurs Bypass Bridge, the federal sections of Bonaventure Expressway and the Honoré Mercier Bridge, as well as the Melocheville Tunnel. The Corporation manages, maintains, and repairs these important Greater Montréal structures to ensure the safe passage of thousands of users every day. It also ensures that these critical structures remain safe, fully functional and aesthetically pleasing both today and in the future. www.JacquesCartierChamplain.ca 

Information: Nathalie Lessard, Director, Communications, JCCBI website: write to Contact us

SOURCE The Jacques Cartier and Champlain Bridges Incorporated


These press releases may also interest you

10 mai 2024
Sky Harbour Group Corporation ("SHG" or the "Company"), an aviation infrastructure company building the first nationwide network of Home-Basing campuses for business aircraft, today announced that it will release its First Quarter 2024 financial...

10 mai 2024
Victoria Gold Corp. ("Victoria" or the "Company") held its Annual General Meeting (the "Meeting") earlier today, May 10, 2024, in Vancouver, British Columbia. Shareholders voted in favour of all items proposed by the board of directors and...

10 mai 2024
Canada Jetlines Operations Ltd. (Cboe CA:CJET) ("Canada Jetlines" or the "Company"), one of Canada's leading leisure airlines, today reported financial results for the first quarter ended March 31, 2024. All financial figures are...

10 mai 2024
WHY: Rosen Law Firm, a global investor rights law firm, reminds purchasers of common stock of QuidelOrtho Corporation between February 18, 2022 and April 1, 2024, both dates inclusive (the "Class Period") of the important June 11, 2024 lead...

10 mai 2024
Applied DNA Sciences, Inc. ("Applied DNA" or the "Company"), a leader in PCR-based DNA technologies, today announced consolidated financial results for its second fiscal quarter ended March 31, 2024. The Company's Form 10-Q can...

10 mai 2024
Striking new work from the acclaimed visual artist behind the Covid flags on the Mall opened to the public today at Freedom Plaza in Washington, D.C. Suzanne Brennan Firstenberg launched her latest work "alienable right to life," at a moving opening...



News published on and distributed by: