Le Lézard
Classified in: Mining industry

Mabilo Stage 1 Cost Update


Not for release to US wire services or distribution in the United States

ANNOUNCEMENT TO THE TORONTO STOCK EXCHANGE AND AUSTRALIAN SECURITIES EXCHANGE

SUBIACO, WESTERN AUSTRALIA / ACCESSWIRE / March 18, 2024 / The Board of RTG Mining Inc. ("RTG", or the "Company") (TSX:RTG)(ASX:RTG) is pleased to provide a cost update for Stage 1 of the Mabilo Project in The Philippines.

A review of the Stage 1 budget conducted by the site team in February 2024 has shown Capital Costs have not materially changed and remain below US$25M as quoted previously. The updated key components of costs for the Stage 1 capital include -

Stage 1 Capital Component

US$M

Mobilisation and Mining Facilities

1.82

Topsoil Removal and Prestrip

5.53

Sterilisation Drilling

0.16

Creek Diversion

0.71

Clearing and Grubbing and Site Prep.

0.91

Relocation/Crop Compensation/Coconut Tree cutting

1.46

Local Community Access Way

0.25

Building and Office Equipment

1.87

Light Vehicles and Other Equipment

1.47

Port

0.89

Land Acquisition

3.65

Contingency (15%)

2.81

Total

21.53

Compared to the last cost review and budget in 2021, Total Operating Costs have reduced slightly with increases in Mining, Crushing, Product Haulage and Mines Department Fund costs being offset by reductions in Shipping, Supervision and Makati Overhead costs. The main operating cost for Stage 1 is detailed below-

Operating Component

US$M

Site G&A

5.55

Mining Supervision/Contractor Overhead

1.62

Mining Load and Haul

7.72

Grade Control

0.69

Clearing & Grubbing/Geotech and Dewatering

0.22

Ancillary Costs

0.50

Site to Port Haulage

1.40

Shipping

8.37

Crushing

0.71

Operating VAT

1.26

Makati Overheads

0.50

Environmental/Community Development/Safety MGB Funds

2.17

El Dore Royalty

1.43

Total

32.14

Commentary:

Commenting on these positive results, RTG's CEO Justine Magee said: "The Stage 1 financials remain very strong despite the pressures on costs we have seen in the industry over the last couple of years and reinforces our confidence in the project as we move into the development phase."

ABOUT RTG MINING INC

RTG Mining Inc. is a mining and exploration company listed on the main board of the Toronto Stock Exchange and the Australian Securities Exchange. RTG is currently focused primarily on progressing the Mabilo Project to start-up having now received a mining permit for the Project, with a view to moving quickly and safely to a producing gold and copper company.

RTG also has a number of exciting new opportunities including the Panguna Project in Bougainville, which it remains committed to while also considering further new business development opportunities.

RTG has an experienced management team which has to date developed seven mines in five different countries, including being responsible for the development of the Masbate Gold Mine in the Philippines through CGA Mining Limited. RTG has some of the most respected international institutional investors as shareholders including Franklin Templeton, Equinox Partners and Sun Valley.

ENQUIRIES

President & CEO - Justine Magee
Tel: +61 8 6489 2900
Email: [email protected]

US Investor Relations Contact
Jaime Wells: +1 970 640 0611
[email protected]

Australia Investor and Media Contact
Sam Burns: +61 400 164 067
[email protected]

COMPLIANCE STATEMENT

Date: 18 March 2024

Authorised for release by: By the Board of Directors

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

The Toronto Stock Exchange has not reviewed nor does it accept responsibility for the accuracy or adequacy of this press release, which has been prepared by management.

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation including, among others, statements made or implied relating to the interpretation of exploration results, accuracy of mineral resource and mineral reserve estimates, parameters and assumptions used to estimate mineral reserves and mineral resources, realization of mineral reserve and mineral resource estimates, estimated economic results of the Mabilo Project, future operational and financial results, including estimated cashflow and the timing thereof, estimated expenditures, expansion, exploration and development activities and the timing thereof, including expectations regarding the DSO, plans for progressing Stage 2 development, completion of a debt funding package, the negotiation of contracts for start up works and offtake arrangements and the completion of merged documentation, RTG's objectives, strategies to achieve those objectives, RTG's beliefs, plans, estimates and intentions, and similar statements concerning anticipated future events, results, circumstances, performance or expectations. All statements, other than statements of historical fact, included herein, are forward-looking statements. Forward looking statements generally can be identified by words such as "objective", "may", "will", "expected", "likely", "intend", "estimate", "anticipate", "believe", "should", "plans", or similar expressions suggesting future outcomes or events. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from RTG's expectations include uncertainties related to fluctuations in gold and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies in the development of RTG's mineral projects; the need to obtain additional financing to develop RTG's mineral projects; the possibility of delay in development programs or in construction projects and uncertainty of meeting anticipated program milestones for RTG's mineral projects and other risks and uncertainties as discussed in RTG's annual report for the year ended December 31, 2022 and detailed from time to time in our other filings with the Canadian securities regulatory authorities available at www.sedar.com. The forward?looking statements made in this announcement relate only to events as of the date on which the statements are made. RTG will not release publicly any revisions or updates to these forward?looking statements to reflect events, circumstances or unanticipated events occurring after the date of this announcement except as required by law or by any appropriate regulatory authority.

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

This announcement has been prepared for publication in Canada and Australia and may not be released to US wire services or distributed in the United States. This announcement does not constitute an offer to sell, or a solicitation of an offer to buy, securities in the United States or any other jurisdiction. Any securities described in this announcement have not been, and will not be, registered under the US Securities Act of 1933, as amended (the "US Securities Act"), or any state securities laws, and may not be offered or sold in the United States except in transactions exempt from, or not subject to, registration under the US Securities Act and applicable US state securities laws.

SOURCE: RTG Mining Inc.



View the original press release on accesswire.com


These press releases may also interest you

27 avr 2024
Shanghai International Automotive Manufacturing Technology & Material Show (AMTS) first held in 2004, is the world's largest automotive engineering technology trade fair. Serving as a display platform for technology and products for 19 years, it is...

26 avr 2024
West Red Lake Gold Mines Ltd. ("West Red Lake Gold" or "WRLG" or the "Company") announces an updated Mineral Resource Estimate ("MRE") effective as of March 1, 2024, on its 100% owned Rowan Mine Deposit, located in the Red Lake Gold District of...

26 avr 2024
Osisko Development Corp. ("Osisko Development" or the "Company") announces the filing of a technical report (the "Technical Report") for the updated mineral resource estimate ("MRE") on its 100%-owned underground Trixie deposit (the "2024 Trixie...

26 avr 2024
Kootenay Resources Inc. ("Kootenay" or the "Company") announces that it has closed its previously announced non-brokered private placement offering (the "Offering") for aggregate gross proceeds of $473,094.95. The Company continues to work towards...

26 avr 2024
Gold Mountain Mining Corp. ("Gold Mountain" or the "Company") (FRA:5XFA) is pleased to announce that Hugh Behroozy has been appointed to its Board of Directors (the "Board") effective immediately.Mr. Behroozy is an...

26 avr 2024
Eagle Bay Resources Corp. ("Eagle Bay" or the "Company") wishes to announce that Jason Birmingham, a founding director of the Company, has resigned from the board to pursue other interests. The Company wishes to thank Mr....



News published on and distributed by: