Taseko Provides Financing and Construction Update for the Florence Copper Project


VANCOUVER, BC, Jan. 16, 2024 /CNW/ - Taseko Mines Limited (TSX: TKO) (NYSE American: TGB) (LSE: TKO) ("Taseko" or the "Company") is pleased to provide an update on financing and construction progress at its Florence Copper project.

On January 15, 2024, the Company signed a definitive agreement with Taurus Mining Royalty Fund L.P. ("Taurus") for the previously announced sale of a US$50 million royalty. The royalty will be for 1.95% of the gross revenue from the sale of all copper from Florence Copper. Funding of the US$50 million is subject to customary closing conditions, and proceeds are expected to be received in early February. The Company also expects to drawdown the first US$10 million of the US$50 million Mitsui financing later this month. With these financings in hand, construction activities at Florence will be accelerating.

To date, site activities have focussed on site preparations, earthworks and civil work for the commercial wellfield. The initial drilling contracts are now being finalized, with drilling of the commercial facility wellfield to commence in February. Additionally, the Company expects to sign a fixed-price contract with TIC Kiewit as general contractor for construction of the SX/EW plant and associated surface infrastructure. All the major plant components are onsite and the build will begin in the second quarter of this year.

Stuart McDonald, President & CEO of Taseko, commented, "Signing of the Taurus royalty agreement is another positive milestone for the project. We are excited to be ramping up construction activities at Florence Copper, which will soon be a major new supplier of low-carbon copper cathode to the US market. 

Site preparations and civil work are well advanced, and we're looking forward to commencing wellfield drilling, with four rigs planned to be onsite initially. Construction of the SX/EW plant and other infrastructure represents a significant portion of the remaining project spend, and a fixed-price contract with TIC Kiewit will reduce inflationary risks, as Arizona continues to be a very active construction market. Our early work on detailed engineering and procurement of long-lead items has significantly de-risked the construction schedule and we're tracking towards first copper production in the fourth quarter of 2025. We're taking a disciplined approach to the buildout of the commercial facility at Florence, while our existing operations at the Gibraltar Mine continue to generate good cashflows in a strong copper price environment."

"As an existing copper producer, Taseko is in an enviable and unique position with near-term, low cost production growth coming from a fully-permitted and environmentally beneficial copper project. With copper now added to the US Department of Energy's critical materials list, market interest in our project and future copper production remains strong," added Mr. McDonald.

Stuart McDonald

President and CEO

No regulatory authority has approved or disapproved of the information contained in this news release.

Caution Regarding Forward-Looking Information

This document contains "forward-looking statements" that were based on Taseko's expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These included but are not limited to:

For further information on Taseko, investors should review the Company's annual Form 40-F filing with the United States Securities and Exchange Commission www.sec.gov and home jurisdiction filings that are available at www.sedar.com, including the "Risk Factors" included in our Annual Information Form.

SOURCE Taseko Mines Limited


These press releases may also interest you

at 08:34
Advanced Technology Services, Inc. (ATS), an industry-leading industrial services provider, is pleased to announce that CEO Jeff Owens will participate in an executive panel discussion on the future of manufacturing at the 2024 Made in America...

at 08:30
AGCO Corporation , a global leader in the design, manufacture, and distribution of agricultural machinery and precision ag technology, announced the grand opening of The Fendt Lodgetm in Jackson, Minnesota,  May 1, 2024. The 16,000-square-foot...

at 08:30
The board of directors of The Timken Company , a global technology leader in engineered bearings and industrial motion, today approved a 3 percent increase in the company's quarterly cash dividend, raising it to 34 cents per share. The dividend is...

at 08:30
Getchell Gold Corp. ("Getchell" or the "Company") is pleased to announce that the Company has closed the third and final tranche of its previously announced debenture financing (the "Debenture Financing"). In this third tranche of the Debenture...

at 08:30
Western Alaska Minerals (the "Company" or "WAM") is pleased to announce that, further to its news releases dated April 18, 2024 and April 22, 2024 and April 26, 2024, due to significant demand, the Company has increased the size...

at 08:05
Avantor, Inc. , a leading global provider of mission-critical products and services to customers in the life sciences and advanced technologies industries, announced that Michael Stubblefield, President and CEO, will be participating in a fireside...



News published on and distributed by: