VANCOUVER, British Columbia, Nov. 15, 2019 (GLOBE NEWSWIRE) -- Nevada Copper Corp. (TSX: NCU) ("Nevada Copper" or the "Company'') announced today that it has SEDAR-filed its quarterly financial statements and management's discussion and analysis for the three and nine months ended September 30, 2019. Additionally, the Company confirms that its Pumpkin Hollow underground copper project (the "Underground Project") is expected to enter production in Q4 2019.

Construction of the processing plant is materially complete and on schedule. Approximately 95,000 tons of development ore has been mined and stockpiled on the run-of-mine pad ready to feed the processing plant. The Company's overall estimated construction costs to complete the Underground Project continue to be within the range announced in the Company's MD&A for Q2 2019.

Construction Progress Update

?  Underground Project development proceeding well:

?  Surface infrastructure and processing equipment at the Underground Project advancing to plan:

Financial Update

?  In order to provide the Company with additional flexibility, the Company has entered into a binding term sheet for a $30 million credit facility (the "Credit Facility"):

Matt Gili, Chief Executive Officer of Nevada Copper, stated "We are now entering the final stages before the commencement of production at Pumpkin Hollow. Our team and contractors are continuing to deliver on schedule as we prepare for production this quarter.  The addition of a credit facility, non-dilutive to shareholders, provides access to additional liquidity as we ramp up copper production during the first half of 2020."

Construction Activity Images

https://www.globenewswire.com/NewsRoom/AttachmentNg/42946d5b-4f62-4d29-9aee-524c7402fb26

https://www.globenewswire.com/NewsRoom/AttachmentNg/9acadaf0-4771-4db2-ac3b-4028f8800321

https://www.globenewswire.com/NewsRoom/AttachmentNg/5fde2893-e102-4cb9-944f-86c420f35258

Further Details of the Credit Facility

The Credit Facility is being arranged by Pala Investments Limited ("Pala"), the Company's largest shareholder. The negotiation of the term sheet has been supervised on behalf of the Company by the independent members of the Company's board of directors.

The Credit Facility would be available for an initial draw of $15 million, and three additional draws of $5 million each at the sole option of the Company, subject to the satisfaction of certain conditions, including for the additional draws Pala having syndicated the facility. The Credit Facility would be a direct obligation of the Company and would not be guaranteed or secured by any of its subsidiaries. It would have a maturity date of September 30, 2021. The Credit Facility bears interest at 9% for the first 12 months of the term and 10% thereafter, subject to certain fees including a 3% arrangement fee. There are no common shares, warrants or other convertible securities issuable in connection with the Credit Facility. The Credit Facility replaces in its entirety Pala's $11.4 million commitment under the equity standby facility that it previously provided to the Company. Further details are available in the Q3 financial statements.

Qualified Persons
The information and data in this news release was reviewed by David Swisher, P.E., SVP of Operations for Nevada Copper, who is a non-independent Qualified Person within the meaning of NI 43-101.

About Nevada Copper
Nevada Copper's (TSX: NCU) Underground Project is in construction with a view to commencement of copper production in Q4, 2019. Located in Nevada, USA, Pumpkin Hollow has substantial reserves and resources including copper, gold and silver. Its two fully-permitted projects include the high-grade Underground Project (under construction) and a large-scale open pit project.

Additional Information
For further information please visit the Nevada Copper corporate website
(www.nevadacopper.com).

NEVADA COPPER CORP.

Matthew Gili, President and CEO
For further information call:

Rich Matthews,
VP Investor Relations
Phone: 604-355-7179
Toll free: 1-877-648-8266
Email: [email protected]

We seek safe harbour.


These press releases may also interest you

at 06:00
Highlights First quarter U.S. GAAP total diluted earnings per share of $11.61, inclusive of gain on aerospace sale, vs. 56 cents in 2023First quarter comparable diluted earnings per share of 68 cents vs. 69 cents in 2023Global beverage can shipments...

at 06:00
Highlights: 13,500-metre maiden drill program completed at the high-grade Polymetallic B26 Deposit; 44 holes drilled with assays from 34 holes pending.Drillhole 1274-24-339 was designed to test the lateral extension of the high-grade lens identified...

at 06:00
Avantor, Inc. , a leading global provider of mission-critical products and services to customers in the life sciences and advanced technology industries, today reported financial results for its first...

at 04:58
Silvercorp Metals Inc. ("Silvercorp") and Adventus Mining Corporation ("Adventus") are pleased to announce that the parties have entered into a definitive arrangement agreement (the "Arrangement Agreement") pursuant to which Silvercorp has agreed...

at 03:29
Company announcement No. 557, 2024 In accordance with Section 30 of the Capital Markets Act it is hereby announced that Nordea Funds Ltd, Finland, yesterday informed H+H International A/S that as per 22 April 2024 Nordea Funds Ltd. increased its...

at 01:26
Rickard Gustafson, President and CEO: "Our first quarter performance marked another step towards a more resilient and competitive SKF. In soft market conditions, we delivered a strong adjusted operating margin of 13.4%, somewhat ahead of Q1 2023. The...



News published on and distributed by: