Tellurian receives FERC scheduling notice for Driftwood LNG


HOUSTON, TX--(Marketwired - December 27, 2017) - Tellurian Inc. (Tellurian) (NASDAQ: TELL) announced today that the Federal Energy Regulatory Commission (FERC) has issued the notice of schedule for environmental review of Driftwood LNG, a proposed 27.6 million tonnes per annum (mtpa) liquefied natural gas (LNG) export facility, and Driftwood Pipeline, a proposed 96-mile, 4 billion cubic feet a day (Bcf/d) pipeline. According to the notice, FERC will issue its final Environmental Impact Statement (EIS) on October 12, 2018, and has established a 90-day Federal Authorization Decision Deadline on January 10, 2019. Assuming a favorable decision, Tellurian expects that this schedule will allow it to begin construction of Driftwood LNG in early 2019, pending a final investment decision by Tellurian.

Estimated Driftwood Project timeline
Catalyst Estimated timeline
Driftwood commercial agreements 1H 2018
Draft Environmental Impact Statement 1H 2018
Final Environmental Impact Statement 12 October 2018
FERC order and Federal Authorization Deadline 10 January 2019
Driftwood final investment decision 1H 2019
Begin construction 1H 2019
Begin operations 2023

About Tellurian Inc.

Tellurian was founded by Charif Souki and Martin Houston and is led by President and CEO Meg Gentle. Tellurian intends to create value for shareholders by building a low-cost, global natural gas business, profitably delivering natural gas to customers worldwide. Tellurian is developing a portfolio of natural gas production, LNG trading, and infrastructure that includes an ~ 27.6 mtpa LNG export facility and an associated pipeline. Tellurian is based in Houston, Texas, and its common stock is listed on the Nasdaq Capital Market under the symbol "TELL".

For more information, please visit www.tellurianinc.com.

Follow us on Twitter at twitter.com/TellurianLNG

CAUTIONARY INFORMATION ABOUT FORWARD-LOOKING STATEMENTS

This press release contains forward-looking statements within the meaning of U.S. federal securities laws. The words "anticipate," "assume," "believe," "budget," "estimate," "expect," "forecast," "initial," "intend," "may," "plan," "potential," "project," "should," "will," "would," and similar expressions are intended to identify forward-looking statements. Forward-looking statements herein relate to, among other things, the capacity, performance, timing, permitting, construction and operations of Driftwood LNG and the Driftwood Pipeline, including our entry into Driftwood commercial agreements and the timing and outcome of a final investment decision. These statements involve a number of known and unknown risks, which may cause actual results to differ materially from expectations expressed or implied in the forward-looking statements. These risks include the matters discussed in Item 1A of Part II of the Quarterly Report on Form 10-Q for the quarter ended September 30, 2017 filed by Tellurian with the Securities and Exchange Commission (the "SEC") on November 9, 2017, and other filings with the SEC, all of which are incorporated by reference herein. The regulatory approvals necessary to construct and complete Driftwood LNG and the Driftwood Pipeline may not be received in a timely manner or at all, or may be granted subject to conditions that are adverse to Tellurian. The forward-looking statements in this press release speak as of the date of this release. Although Tellurian may from time to time voluntarily update its prior forward-looking statements, it disclaims any commitment to do so except as required by securities laws.


These press releases may also interest you

at 10:31
On May 9, The 8th Global ICT Energy Efficiency Summit, themed "Green Site, Building a Brighter Future", was held in Bangkok, Thailand. At this summit, Site Power Facility Domain of Huawei Digital Power launched the All-Scenario Smart Telecom Power...

10 mai 2024
With reference to the announcement published on May 6, 2024 containing the results of Noble Corporation plc ("Noble") for the quarterly period ended March 31, 2024, Noble hereby announces the publication of its quarterly report on Form 10-Q for the...

10 mai 2024
ARC Resources Ltd. ("ARC" or the "Corporation") is pleased to announce that its shareholders approved all resolutions at its Annual and General Meeting of Shareholders (the "Meeting") held on May 10, 2024....

10 mai 2024
Crescent Point Energy Corp. ("Crescent Point", or the "Company") and held its Annual and Special Meeting of Shareholders ("AGM" or "the meeting") on May 10, 2024. During the business portion of the meeting, shareholders approved all resolutions...

10 mai 2024
Saville Resources Inc. (the "Company") announce it has increased the proposed size of its previously announced non-brokered private placement (see press release of May 1, 2024 for further details) to a new maximum of up to 20,000,000 units...

10 mai 2024
Bechtel today announced the completion of the jacking and setting process for Mobile Launcher 2 at Kennedy Space Center. This achievement is a critical step in the process to design, build, and commission NASA's new mobile launcher. The milestone was...



News published on and distributed by: