VANCOUVER, BRITISH COLUMBIA--(Marketwired - March 29, 2017) - Corex Gold Corp. (TSX VENTURE:CGE) ("Corex" or the "Company") is continuing construction and mining activities at its 100%-owned Santana heap-leach gold project in Sonora, Mexico.

Jaw crushing and loading started on Nicho Norte zone in late November 2016. A total of 11,210 tonnes of material was crushed in November and December and loaded onto the 1st leach pad. An additional 11,989 tonnes were loaded in January bringing the total to 23,199 tonnes. The pad loading was completed on January 26, 2017. The heap was contoured and the surface broken up in preparation for leaching.

Construction continued on the bulk test process plant and the completion of the distribution system plumbing with several application methods of leach fluid tested. Application of charged leachant to establish alkaline pH has begun with metal leaching to commence later this month.

A second leach pad will allow a separate batch of finer crushed material to be tested to determine the leach and cost characterization of much finer crushing. The results from the two bulk leach pads will be utilized by the Company to verify metallurgical viability of heap leaching and to optimize the most efficient operating methods and equipment.

Construction of the 2nd leach pad, which connects to the first leach pad, is in progress. The 2nd leach pad is about 4,500 square meters. The earthwork or moving of material is substantially complete. The HDPE liners have been ordered and should be installed in early March 2017. This will provide a total leach pad of about 9,000 square meters.

(For recent photos of the Santana heap-leach gold project click here).

"This is an exciting time for shareholders, as we commence our bulk mining and process testing on our Santana Gold Project," said Craig Schneider, Corex's President and CEO.

The Company is not basing its production effort on a feasibility study with demonstrated mineral reserves and estimated economic and technical viability. As a result, the Company acknowledges and accepts the higher risk of failure with uncertainty of unverified economic and technical outcome. Corex believes the past experience and prudent track record of Chester Millar developing this type of mine helps ameliorate possible technical risk.

Mel Herdrick P. Geo., is the acting Qualified Person as defined by National Instrument 43-101. He has reviewed and approved the preparation of the technical information in this release. He is a shareholder of the company.

The reader should be cautioned the Company has neither completed economic nor technical feasibility studies or metallurgical studies confirming the projected production capacity at Santana and there is no certainty the Company's plans will be economically viable.

About Corex Gold Corp.

Corex Gold Corp. is a Canadian resource company focused on achieving near-term economic gold production from its 100% owned flagship property, Santana Project, Sonora State, Mexico.

Cautionary Statement:

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. The foregoing information may contain forward-looking statements relating to the future performance of Corex Gold Corp. Forward-looking statements, specifically those concerned with future performance are subject to certain risks and uncertainties, and actual results may differ materially. These risks and uncertainties are detailed from time to time in Corex Gold Corp.'s filings with the appropriate securities commissions.


These press releases may also interest you

3 mai 2024
Eastern Platinum Limited (JSE: EPS) ("Eastplats" or the "Company") is pleased to report that it has filed its Audited Consolidated Financial Statements for the fiscal year ended December 31, 2023 and the corresponding Management's Discussion and...

3 mai 2024
Kolibri Global Energy Inc. (the "Company") announces that, further to the Company's news released date May 2, 2024, the Company has completed the filing of the Company's annual information form, annual audited financial statements, management's...

3 mai 2024
Ultra Lithium Inc. ("Ultra Lithium" or the "Company") is providing this bi-weekly default status report in accordance with National Policy 12-203 Management Cease Trade Orders ("NP 12-203"). On March 4, 2024, the Company announced that effective...

3 mai 2024
Galway Metals Inc. ("Galway" or the "Corporation") is pleased to announce that further to its press release dated April 25, 2024, it has closed the second and final tranche of its non-brokered private placement (the "Private Placement"). The second...

3 mai 2024
Taiga Building Products Ltd. announces detailed voting results from the annual general meeting of shareholders of the Company held on May 2, 2024. ...

3 mai 2024
Vizsla Silver Corp. ("Vizsla Silver" or the "Company") is pleased to announce that it has now issued 448,137 common shares (the "Consideration Shares") for the previously announced asset purchase agreement (the "Acquisition Agreement") dated March...



News published on and distributed by: