Le Lézard
Classified in: Business
Subjects: NEW PRODUCTS/SERVICES, EARNINGS, CALENDAR OF EVENTS, STOCK/OTHER MARKET NEWS, MISCELLANEOUS

Orocobre Limited Quarterly Report of Operations for the Period Ended 31 March 2019


BRISBANE, Australia, April 16, 2019 (GLOBE NEWSWIRE) --

MARCH QUARTER 2019 KEY HIGHLIGHTS1

OLAROZ LITHIUM FACILITY (ORE 66.5%)2

LITHIUM GROWTH PROJECTS

BORAX ARGENTINA

CORPORATE

1 All figures presented in this report are unaudited
2 All figures 100% Olaroz Project basis
3 Orocobre report price as "FOB" (Free On Board) which excludes additional insurance and freight charges included in "CIF" (Cost, Insurance and Freight or delivered to destination port) pricing. The key difference between an FOB and CIF agreement is the point at which responsibility and liability transfer from seller to buyer. The Company's pricing is also net of TTC commissions but excludes export taxes. FOB prices are used by the company to provide clarity on the sales revenue that flows back to SDJ, the joint venture company in Argentina
4 Excludes royalties, export tax and corporate costs

CAUCHARI JOINT VENTURE

(ADVANTAGE LITHIUM OPERATOR 75% / OROCOBRE 25%)

OLAROZ LITHIUM FACILITY

Click here for more information on Olaroz

SAFETY

Unfortunately, an incident occurred at Olaroz during the quarter resulting in a Lost Time Injury (LTI) being recorded. The person has now returned to work on full duties. As of 31 March, operations had achieved 20 days without an LTI.

Based on the in-depth Safety Audit conducted by DuPont, which evaluated Sales de Jujuy S.A. (SDJ) safety performance, an improvement roadmap was developed to address the key risks and priorities identified. The Company and DuPont are continuing to work together to develop and foster the Company's safety culture.

PRODUCTION, SALES AND OPERATIONAL UPDATE

PRODUCTION AND SALES

During the quarter Orocobre provided an update on the impact of rainfall and expected production for the remainder of the financial year. Rainfall exceeded the same period in 2017 and 2018 resulting in dilution of brine feedstock. There were no material production stoppages, nor disruption to the import of supplies or the export of finished product. However, FY19 was the highest Q3 production achieved to date, up 10% on PCP. Orocobre continues to expect FY19 production to be approximately the same as that achieved in FY18. Production for the March quarter was 3,075 tonnes up from 2,802 tonnes on PCP and down 19% from 3,782 tonnes in the December quarter.

Sales were 3,530 tonnes of lithium carbonate with a realised average price of US$9,451/tonne on a FOB basis and total sales revenue of US$33.4 million. The average price received during the quarter was 11% down QoQ. Prices achieved outside of China were influenced by growing competition from increased Chinese exports responding to subdued domestic demand.

Gross cash margins for the quarter (excluding export tax) remained strong at 56% or US$5,258/tonne but down 20% QoQ and 43% on PCP. Operating costs (on a cost of goods sold basis, excluding export tax) were US$4,193/tonne up 6% QoQ and down 4% on the March 2018 quarter. An 11% QoQ decrease of the realised average price received contributed to an 11% QoQ decrease in gross cash margin achieved.

      
MetricMarch
quarter 2019
December
 quarter 2018
Change QoQ
(%)
PCP
(Mar FY18)
Change PCP
(%)
Production (tonnes)3,0753,782-19%2,80210%
Sales (tonnes)3,5303,01917%3,05216%
Average price received (US$/tonne) 39,45110,587-11%13,533-30%
Cost of sales (US$/tonne)44,1933,9746%4,356-4%
Revenue (US$M)33.4324%41.3-19%
Gross cash margin (US$/tonne)5,2586,613-20%9,177-43%
Gross cash margin (%)56%62%-11%68%-18%
Export tax (US$/tonne)776882-12%  
      

OPERATIONAL UPDATE

The operational strategy has been focused on safety and quality. Special attention is being devoted to improving the lithium grade of brine feedstock - "brine quality'. Improved brine quality has multiple benefits including higher lithium recoveries, lower cost of production and increased product quality and consistency.

Battery grade carbonate production was temporarily suspended while brine quality recovered during March following rain in January and February. Customers requiring battery grade lithium carbonate were supplied from inventory during this period. Production of battery grade lithium carbonate will recommence in the June quarter.

Six of the eight Stage 1 harvest ponds have now been cleared of harvestable salt which precipitated through the evaporation process. The final two ponds are currently being harvested. Pond harvesting enables the recovery of brine that is retained in the salts which can then be processed in the plant. With the increase in area from development of Stage 2 ponds, future salt harvesting will become a continuous process where ponds are harvested on a rotational basis over a three year cycle.

FUTURE PRODUCTION GUIDANCE

Orocobre expects that full-year production for FY19 will be approximately the same as that achieved in FY18 which was 12,470 tonnes. Year to date production has been 9,150 tonnes which is up from 8,874 tonnes over the same period in FY18.

STAGE 2 EXPANSION AT OLAROZ

The Stage 2 Expansion of Olaroz is fully funded with cash and proposed debt funding arrangements.

PROGRESS TO DATE

Construction of key items for the Stage 2 Expansion such as ponds, secondary liming plant, roads and camp upgrades continued to advance during Q3 FY19.

At Quarter end approximately US$29 million has been spent on the first phase of expansion activities including the construction of new roads, vegetation clearing, construction of new evaporation and harvest ponds, secondary liming plant, eight boreholes (currently four drilling rigs onsite with two more contracted to start mid-May). The expansion of existing site infrastructure and camp accommodation continued including a new health center for the extended work force, office space for the expansion team and warehouses for equipment. The new camp accommodation facilities and catering facilities were completed during the quarter.

As part of the Stage 2 Expansion the process flow diagrams, layouts and equipment lists were finalised during the quarter. An Engineering, Procurement, Management and Construction (EPCM) company has been selected after a tender process. The successful company was Jacobs, a well-known international construction company with more than 20 years' experience in Argentina (through its subsidy company CH2M Hill) who has built many mining/chemical/petroleum plants. Jacobs in association with WorleyParsons (a company that has more than 20 years' experience in the design and construction of lithium plants in Chile and Argentina) will oversee the chemical process review and design. The project's budget and timeline are now being reviewed by Orocobre and Jacobs.

Six new harvest ponds (16A, 16B, 17A, 17B, 18A & 18B) have been filled with concentrated brine and are operational, replacing pond area that is temporarily unavailable due to salt harvesting activities as discussed earlier. Two additional harvest ponds (R11 & R12) were completed during the quarter and will be filled with concentrated brine during the June quarter.

Two new evaporation ponds (15A & 15B) have now been filled with concentrated brine and are operational. Vegetation clearing and construction of three new evaporation ponds has commenced (14C, 20A & 21A). Brine transfer ducts are also under construction.

Engineering and civil works for the secondary mobile liming plant were completed during the quarter, including the construction of concrete slabs and the delivery of tanks with installation to commence during the June quarter. The secondary liming plant will have the capacity to treat up to 300 l/s of brine.

During the quarter construction began on a new reactor for the existing primary liming plant. This reactor will enable the primary liming plant to process a higher flow rate of brine before the Stage 2 liming plant is built permitting brine stocks to be increased and facilitating the rapid filling of Stage 2 ponds. A mobile secondary liming plant is expected to be installed by late April. Between both plants, there will be capacity to treat up to 600 l/s of brine.

SHARED VALUE PROGRAM AND COMMUNITY

SDJ's community engagement and investment initiatives during the March quarter continued in accordance with the Company's Shared Value approach.

EDUCATION

With the start of the 2019 calendar year, SDJ welcomed a new intake of students to the employee education program. SDJ continued towards its goal of having 100% of SDJ's community employees holding secondary education qualifications by 2025.

Enhancing educational infrastructure within communities remains a key focus, with a new music hall and laboratory facility inaugurated in Olaroz and an Institutional Improvement Plan implemented collaboratively with Susques Primary School to renovate amenities for local students.

TRANSPARENCY

Initiatives included a presentation and consultation with communities on the most recent update to SDJ's Environmental Impact Assessment as well as quarterly environmental monitoring activities conducted with participants from local communities.

EMPOWERMENT

The focus during the quarter was on the evaluation of community suppliers to identify opportunities for focused development and capacity building. SDJ is committed to ensuring these suppliers are supported to not only stabilise and scale their operations over coming years but also to operate in a socially and environmentally responsible manner.

PRODUCTION AND NATURAL RESOURCES

Programs to strengthen local artisanal production were progressed during the quarter, with significant developments in the fibre spinning project in Huancar and the development of a ?waste upcycling' initiative in Susques to build awareness of individual responsibility and contribution to protect the local environment.

MARKET AND SALES

LITHIUM MARKET

Orocobre views current market conditions as a short-term correction which has led much of the market to overlook strong long-term demand fundamentals driven by growth in the electric vehicle (EV) and energy storage system (ESS) segments. Accordingly, Orocobre maintains long-term demand forecasts in line with the consensus of other major producers in the range of 18% to 20% CAGR between 2018 and 2025.

SEABORNE SUPPLY

During Q3 FY19, the spread of pricing in the seaborne market widened to reflect an increasingly complex market environment as factors, including strategic partnering, product qualification periods, broad product specification ranges, contract length and time at which the contract price was negotiated, resulted in a greater range of pricing outcomes. Seaborne prices and market balance were unaffected by widespread rainfall across South America having a lower-than-anticipated impact of ~5 kt LCE based on supplier guidance. Nonetheless, there may be potential for a delayed impact later in the year as the downstream battery chain enters the peak production period and should the Chinese market and economy improve.

CHINESE MARKET

Following the conclusion of China's New Year holiday period, independent Chinese conversion plants demonstrated little appetite to build inventory despite widespread announcements of lower spodumene prices in 2019. Similarly, Chinese lithium chemical customers were resistant to establishing long-term agreements instead preferring to negotiate on a shipment-by-shipment basis, as communicated by key suppliers during the most recent earnings calls. As a result, Chinese imports continued to decline as suppliers became increasingly focused on key long-term growth markets with less volatility including South Korea, Japan and Europe.

CHINESE EV POLICY & MARKET

The compound effect of China's economic instability and the later-than-anticipated NEV (New Electric Vehicle) policy announcement meant there was little to drive Chinese demand. After much anticipation, the updated Chinese NEV policy was announced late in the quarter on 26 March indicating subsidies would be cut by between 47% and 60% for EV's that met the minimum range requirement. Orocobre views the progressive reduction to China's EV policy as an effective way of improving the technical standards and performance of China's battery and EV industry. Despite the current industry restructuring, China continues to record robust electric vehicle sales achieving 198% year-on-year growth in January 2019 (includes full battery EV, BEV and plug-in hybrid PHEV), while EV sales as a proportion of total sales increased to 8.1% in December 2018 compared with 3.8% a year earlier.

QUALIFICATIONS & CONTRACTS

The Joint Venture through exclusive sales agent TTC is currently progressing commercial discussions with customers in regard to longer term supply contracts for both purified and prime grade products in the battery and non-battery market segments. The Joint Venture's intention is to significantly increase the proportion of business under longer term (> 1 year) contractual arrangements underpinned by sound value propositions defined and agreed with customers.

NARAHA LITHIUM HYDROXIDE PLANT

FINAL INVESTMENT DECISION APPROVED

Subsequent to the end of the quarter Orocobre, TTC and JV boards approved the FID for the Naraha Lithium Hydroxide Plant to be built in Japan. Orocobre will hold a 75% economic interest in the project with operations to be managed by TTC.

Construction of the Naraha Lithium Hydroxide Plant is expected to commence during H1 CY19 with commissioning to commence during H1 CY21. The Naraha Joint Venture will be overseen by a Joint Technical Committee during construction and commissioning. The Joint Technical Committee will comprise both TTC and Orocobre representatives.

Feedstock for the 10,000 tonne per annum (tpa) Naraha Lithium Hydroxide Plant will be sourced from the Olaroz Lithium Facility's Stage 2 Expansion that will produce primary grade (>99.0% Li2CO3) lithium carbonate.

The total Engineer-Procure-Construct (EPC) contract value is expected to be approximately JPY8.6 billion (US$77.6 million1, excluding VAT) following detailed engineering studies, the inclusion of a calciner to recycle lime used in processing and significant automation of the process. The Joint Venture Company will be entitled to a Japanese government subsidy of JPY3 billion (US$27.1 million1) which will reduce net capital costs to JPY5.6 billion (US$50.5 million1, excluding VAT). Operating costs (excluding primary grade lithium carbonate feedstock) for the Naraha Lithium Hydroxide Plant are estimated to be approximately US$1,500/tonne.

Sales of lithium hydroxide will be managed by TTC as exclusive sales agent under a similar joint marketing arrangement to that operating for lithium carbonate from the Olaroz Lithium Facility. The majority of production is expected to be delivered to the Japanese battery industry.

A cathode manufacturing plant is already in operation in the immediate vicinity and plans have been announced to develop a battery manufacturing facility nearby.

FINANCING

The Naraha Lithium Hydroxide Plant will be funded through a combination of JPY9.1 billion (US$82.1 million1) of term/bridging loans and JPY1.0 billion (US$9.0 million1) of shareholder equity. Orocobre will contribute JPY750 million (US$6.8 million1) equity and TTC will contribute JPY250 million (US$2.3 million1).

Two project loans have been provided by Japanese banks at effective interest rates of <1%. All of the financing is non-recourse to Orocobre.

   
Term LoanJPY6.1 billionUS$55.0 million1
Subsidy Bridge LoanJPY3.0 billionUS$27.1 million1
EquityJPY1.0 billionUS$9.0 million1
TotalJPY10.1 billionUS$91.1 million1
   

In addition, a JPY0.8 billion (US$7.2 million1) VAT Bridging Loan has been established to cover the period between VAT payment and VAT refunds on project expenditure.

The subsidy of approximately JPY3.0 billion (US$27.1 million1) from the Japanese government is expected to be received in H1 CY21 once the project reaches mechanical completion.

1 The EPC contract and all financing is denominated in Japanese Yen and has been converted at a JPYUSD exchange rate of 110.9

The Term Loan will be repaid from operating cash flow with a maximum term of seven years. The Subsidy Bridge Loan will be repaid upon receipt of Subsidy payments and the VAT Bridge Loan will be repaid from VAT refunds.

BORAX ARGENTINA

SAFETY

An incident occurred at the Sijes mine during the quarter resulting in an LTI being recorded. As of 31 March, the Sijes mine achieved 46 days without an LTI, Tincalayu had achieved 704 days without an LTI and Campo Quijano had achieved 387 days without an LTI. Prior to an LTI being recorded at the Sijes mine during February, the site had achieved a record of 1,249 days without an LTI.

PRODUCTION, SALES AND OPERATIONAL UPDATE

Borax Argentina continues to demonstrate improved year on year sales performance. Business development projects are being progressed and will continue to remain a key area of focus in CY19. The business has demonstrated continuous improvement on cost reduction and unit costs continue to be controlled at, or near record lows.

Q3 FY19 delivered some very positive results for Borax Argentina with 13,041 tonnes sold (+21% QoQ and +44% PCP) which included a spot sale of 2,312 tonnes of low value mineral product. Removing this transaction from the quarterly sales volume delivers a result of 10,729 tonnes which is in line with Q2 FY19 and up 18% on PCP.

Total sales revenue was up 4% QoQ and the average price received after adjusting for the low value mineral sale was up 3.5% QoQ.

COMBINED PRODUCT SALES VOLUME BY QUARTER

  
Previous Year QuartersRecent Quarters
June 201711,398June 201810,590
September 20178,543September 20189,407
December 20178,341December 201810,741
March 20189,079March 201913,041
    

TINCALAYU EXPANSION STUDY

The study on an expansion of the Tincalayu refined borates operation is in the final stage of internal review. Approvals have been received for a new gas pipeline to supply the expanded plant and initial cost estimates are under review.

ADVANTAGE LITHIUM

Advantage Lithium Corp (TSV:AAL) manages a portfolio of high-quality assets in Argentina, including the Cauchari Joint Venture in which Orocobre holds a 25% interest. Orocobre also holds approximately 33.5% of the issued shares of AAL.

CAUCHARI JV PROJECT

The Cauchari Project is located in Jujuy province in NW Argentina.

During the quarter Advantage Lithium released an updated resource estimate for the Cauchari JV property. The updated resource estimate (see ASX Release dated 7 March 2019) has more than doubled from the previous resource announced in May 2018. A Pre-Feasibility Study will now be conducted to determine the optimal processing and development option for the expanded resource.

The resources have been broken into six different geological units which are classified between Measured, Indicated and Inferred resources, with the classification reflecting differences in the level of available sample information. The resource estimate is presented in the table below.

Cauchari Project Lithium Resource Estimate; March 2019

     
 Measured (M)Indicated (I)M+IInferred
Aquifer volume (km3)9.720.930.710.7
Mean specific yield6%6%6%6%
Brine volume (km3)0.61.21.90.6
Li mean grade (g/m3)35262927
Li mean concentration (mg/l)527452476473
Resource (tonnes)345,000550,000900,000290,000
Lithium Carbonate Equivalent1,850,0002,950,0004,800,0001,500,000
     

Results of the brine chemistry analysis carried out as part of the updated resource estimate confirm the Cauchari brine is similar in composition to the brine in the adjacent Olaroz Salar from which Orocobre is successfully producing lithium carbonate using conventional lithium processing technology. The table below provides a summary of the Cauchari brine characteristics.

Cauchari brine chemistry characteristics

       
Samples RatioArchibarca FanClayEast FanHaliteDeep SandWest Fan
Mg/Li2.32.51.62.72.53.2
SO4/Li26.239.788.744.338.138.4
       

CORPORATE AND ADMINISTRATION

FINANCE

VAT

VAT refunds of approximately ~US$0.5 million were received during the quarter. Approximately US$2 million of peso denominated returns were lodged and are expected to be received next quarter. The current VAT claims awaiting payment are US$3.3 million.

CASH BALANCE

As at 31 March 2019, Orocobre corporate had available cash of US$265.7million. The US$18.3 million cash reduction from the prior quarter was the result of a US$15 million shareholders loan made to the SDJ joint venture to fund Olaroz expansion activities, US$1.5 million in corporate costs, US$1.1 million in payments to other group entities, US$0.8 million in Cauchari JV expenditure, US$1.3 million funding to Borax (mainly to repay banking facilities), US$0.7 million LiOH plant and US$0.1 million of forex losses. This expenditure was partially offset by US$2.2 million interest income.

Including SDJ and Borax cash and project debt, net group cash at 31 March 2019 is US$192.9 million, down from US$207.7 million at 31 December 2018.

The AR$/US$ exchange rate devalued by 15% during the quarter with government intervention on interest rates and other measures. At 31 December 2018 the rate was AR$37.70/US$ and this weakened to AR$43.35/US$ at 31 March 2019 whilst inflation for the same period was approximately 11%. This devaluation partially offsets the impact of the export tax that was announced in 2018.

When looking at the accumulated 12-month period from 1 April 2018 to 31 March 2019, devaluation of the AR$ against the US$ was 115% versus inflation of approximately 53%. This resulted in balancing US$ costs for ARS peso denominated expenses for the period considering the delayed response in devaluation vs inflation in previous periods. As a result, costs were lower for Borax Argentina and to a lesser extent, SDJ. Over time, inflation and devaluation generally cancel each other out.

OTHER MATTERS

During the quarter Mr Martín Pérez de Solay was appointed to the role of Managing Director and Chief Executive Officer taking over from Mr Richard Seville. Mr Seville ceased formal employment with Orocobre on 16 April following a period of annual leave. The Board has approved the vesting of 145,073 of his 316,490 outstanding performance rights consistent with the Good Leaver provisions of the Orocobre Performance Rights and Options Plan (PROP). Mr Seville will also be eligible to participate in the Orocobre 2018/19 Short Term Incentive (STI) plan on a pro rata basis. There has been no payment for the 12 month fixed remuneration termination benefit as per his service agreement following notice. The vesting of outstanding performance rights is in recognition of Mr Seville's significant contribution to Orocobre and his participation in the transition with our new CEO.

For more information please contact:
Andrew Barber
Investor Relations Manager
Orocobre Limited
T: +61 7 3871 3985
M: +61 418 783 701
E: [email protected]
W: www.orocobre.com.au

https://twitter.com/OrocobreLimited
https://www.linkedin.com/company/orocobre-limited
https://www.facebook.com/OrocobreLimited/
https://www.instagram.com/orocobre/
https://www.youtube.com/channel/UCuLtQ_xM61u8EFUzUa8YG_Q

Click here to subscribe to the Orocobre e-Newsletter


These press releases may also interest you

at 02:17
ValueAct Capital ("ValueAct"), a global investment firm that has been a major shareholder of Seven & i Holdings ("Seven & i") since 2020, today expressed support for recent announcements by Seven & i:...

at 02:05
PureTech Health plc ("PureTech" or the "Company") plans to publish its Annual Report and Accounts and financial results for the year ended December 31, 2023, on Thursday, April 25, 2024. A presentation and conference call to discuss the results...

at 02:05
Hansa Biopharma, the pioneer in immunomodulatory enzyme technology for rare IgG mediated diseases, today announced its business update and year-end report for January to March 2024. Highlights for the first quarter of 2024      Strong commercial...

at 02:00
Lithium Americas Corp. ("Lithium Americas" or the "Company") announced the pricing of its previously announced underwritten public offering (the "Offering") of 55,000,000 of its common shares (the "Common Shares") at a price to the public of $5.00...

at 02:00
One United Properties, the leading green investor and developer of residential, mixed-use and office real estate in Romania, has launched ONE 2030, a transformative strategy to reshape Bucharest's real estate market and showcase the city as a market...

at 01:51
MHWirth AS ("MHW") has received an arbitration award issued by a tribunal under the rules of the Singapore International Arbitration Centre (SIAC) in a dispute with Jurong Shipyard Pte Ltd ("Jurong") arising out of Jurong's termination of four...



News published on and distributed by: