2017 marks year of progress for nation's only new nuclear units


ATLANTA, Dec. 12, 2017 /PRNewswire/ -- 2017 was a year of construction progress for the Vogtle expansion with 6,000 people from across the country onsite working to move the Vogtle nuclear expansion forward. The new units at Plant Vogtle (co-owned by Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities) are the only new nuclear units currently under construction in the United States and, once complete, will generate enough electricity to power approximately 500,000 homes and businesses. 

Significant milestones and announcements this year included:

To view all of the progress made this year, and since the beginning of construction, visit the Georgia Power YouTube Channel and view new photos added each month in the Plant Vogtle 3 & 4 Online Photo Gallery.

Vogtle Project Review & Cost Update
The Georgia PSC is reviewing the recommendation to move forward filed on August 31 and is expected to make a decision regarding the future of the Vogtle 3 and 4 project as part of the 17th Vogtle Construction Monitoring (VCM) proceeding. Read the 17th VCM Report here.

From the beginning of the Vogtle expansion, Georgia Power has worked to pursue all available benefits for customers and minimize the impact of the new units on electric bills. In addition to this month's announcement that the Vogtle co-owners have reached an agreement to receive 100 percent of parent guarantee funds available from Toshiba (approximately $3.2 billion) by Dec. 15, 2017, the company recently announced a conditional commitment of approximately $1.67 billion in additional loan guarantees for the project from the U.S. Department of Energy (DOE). Today, after including anticipated customer benefits from federal production tax credits, interest savings from loan guarantees from the DOE and the fuel savings of nuclear energy, the projected peak rate impact to Georgia Power retail customers is approximately 10 percent, with 5 percent related to the project already in rates ? well below original projections of approximately 12 percent.

Final approval and issuance of the additional loan guarantees by the DOE cannot be assured and are subject to the negotiation of definitive agreements, completion of due diligence by the DOE, receipt of any necessary regulatory approvals, and satisfaction of other conditions.

About Georgia Power
Georgia Power is the largest electric subsidiary of Southern Company (NYSE: SO), America's premier energy company. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company's promise to 2.5 million customers in all but four of Georgia's 159 counties. Committed to delivering clean, safe, reliable and affordable energy at rates below the national average, Georgia Power maintains a diverse, innovative generation mix that includes nuclear, coal and natural gas, as well as renewables such as solar, hydroelectric and wind. Georgia Power focuses on delivering world-class service to its customers every day and the company is consistently recognized by J.D. Power and Associates as an industry leader in customer satisfaction. For more information, visit www.GeorgiaPower.com and connect with the company on Facebook (Facebook.com/GeorgiaPower), Twitter (Twitter.com/GeorgiaPower) and Instagram (Instagram.com/ga_power).

Cautionary Note Regarding Forward-Looking Statements
Certain information contained in this communication is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning the new agreement with Toshiba, expected benefits of the DOE loan guarantees, expected rate impacts and other future actions related to Plant Vogtle Units 3 and 4. Georgia Power cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of Georgia Power; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Georgia Power's Annual Report on Form 10-K for the year ended December 31, 2016, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: the impact of any inability or other failure of Toshiba to perform its obligations under its guarantee and the new agreement; the impact of any failure to extend the in-service deadline for federal production tax credits; the impact of any failure to amend the DOE loan guarantee to allow for additional borrowings; state and federal rate regulations and the impact of pending and future rate cases and negotiations; the impact of recent and future federal and state regulatory changes, as well as changes in application of existing laws and regulations; current and future litigation, regulatory investigations, proceedings, or inquiries; available sources and costs of fuels; effects of inflation; the ability to control costs and avoid cost overruns during the development construction and operation of facilities, which include the development and construction of generating facilities with designs that have not been finalized or previously constructed; the ability to construct facilities in accordance with the requirements of permits and licenses, to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; advances in technology; legal proceedings and regulatory approvals and actions related to Plant Vogtle Units 3 and 4, including Georgia Public Service Commission approvals and Nuclear Regulatory Commission actions; interest rate fluctuations and financial market conditions and the results of financing efforts; changes in The Southern Company's or Georgia Power's credit ratings, including impacts on interest rates, access to capital markets, and collateral requirements; the impacts of any sovereign financial issues, including impacts on interest rates, access to capital markets, impacts on foreign currency exchange rates, counterparty performance, and the economy in general, as well as potential impacts on the benefits of DOE loan guarantees; and the effect of accounting pronouncements issued periodically by standard setting bodies. Georgia Power expressly disclaims any obligation to update any forward-looking information. 

 

The first steam generator is placed for Vogtle Unit 3. The 1.4 million-pound steam generator marked the first major lift with Southern Nuclear in charge of oversight activities at the construction site.

6,000 workers from across the country remain onsite working to move the Vogtle expansion forward at the end of 2017.

Georgia Power logo. (PRNewsFoto/Georgia Power)

SOURCE Georgia Power


These press releases may also interest you

at 18:38
Clearview Resources Ltd. ("Clearview" or the "Company") is pleased to announce its reserves report and financial and operational results for the year ended December 31, 2023....

at 18:00
Alvopetro Energy Ltd. ("Alvopetro") announces that it has filed a request for an emergency arbitration (the "Emergency Arbitration Application") before the International Court of Arbitration of the International Chamber of Commerce ("ICC") in...

at 17:30
ShaMaran Petroleum Corp. ("ShaMaran" or the "Company")  announces that its Annual General and Special Meeting of Shareholders (the "Meeting") will be held in Canada on Tuesday, June 25, 2024, at 8:00 am (Pacific Time) at 1055 Dunsmuir Street, Suite...

at 17:27
? Perpetual Energy Inc. ("Perpetual", or the "Company") is pleased to announce the completion of its previously announced early redemption of its 8.75% senior secured third-lien notes maturing January 23, 2025 (the "2025 Senior Notes"), with the...

at 17:25
The Honourable Jonathan Wilkinson, Minister of Energy and Natural Resources, and the Honourable Rechie Valdez, Minister of Small Business, will hold a media availability to highlight the federal budget's commitments to getting projects built faster...

at 17:00
Advantage Energy Ltd. ("Advantage" or the "Corporation") is pleased to report 2024 first quarter financial and operating results. Advantage continued to execute on its three-year plan in the first quarter, delivering exceptional well results and...



News published on and distributed by: