Met-Ed Conducting Inspections and Maintenance Prior to Summer Season to Help Enhance Customer Service Reliability


READING, Pa., June 11, 2018 /PRNewswire/ -- With the upcoming hot summer months expected to produce higher electric usage, Metropolitan Edison Company (Met-Ed), a FirstEnergy Corp. (NYSE: FE) subsidiary, is completing inspections and conducting equipment maintenance in its 14-county eastern and south-central Pennsylvania service area to enhance service reliability for customers.

Met-Ed Logo (PRNewsfoto/FirstEnergy Corp.)

Cost-effective helicopter patrols have completed inspections on more than 1,300 miles of transmission lines located in the Met-Ed area.  The inspections are designed to look for damaged wire, broken cross arms, failed insulators, and other hardware problems not visible from the ground.  Any potential reliability issues identified during the inspection will be addressed immediately.

On the ground, Met-Ed crews are inspecting distribution circuits, including transformers, capacitors, reclosers and lightning arrestors to ensure the equipment is operational and the lines are ready to perform efficiently when demand for electricity increases during the summer, typically due to air conditioning usage.

"Summer heat and humidity results in our customers using more fans and air conditioning to stay cool," said Ed Shuttleworth, Met-Ed regional president.  "By conducting proactive inspections and equipment maintenance, we help ensure system reliability to meet this increased demand for electricity."

In addition, a team of Met-Ed and FirstEnergy employees recently conducted readiness exercises to test the company's restoration process used to repair storm-related power outages.  Storm drills are becoming more common in the utility industry in the wake of severe weather over the last several years.

Tree trimming is another key to preparing the Met-Ed system to meet the rigors of summer operations by maintaining proper clearances around electrical systems and helping to protect against tree-related outages.  Met-Ed tree contractors have trimmed approximately 900 circuit miles of electric lines since January and expect to trim another 2,600 miles by year end.

For updated company information, including hot weather tips, customers are urged to visit the 24/7 Power Center at www.firstenergycorp.com/outages.

In addition to the work being done by company employees, summer also is a time when roofers, home builders, lawn service workers and other contractors work long hours.  To help stay safe around electrical equipment while on the job, FirstEnergy offers important tips at www.firstenergycorp.com/contractorsafety.

Met-Ed serves approximately 560,000 customers in 14 Pennsylvania counties.  Follow Met-Ed on Twitter @Met Ed and on Facebook at www.facebook.com/MetEdElectric.

FirstEnergy is dedicated to safety, reliability and operational excellence.  Its 10 electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York.  The company's transmission subsidiaries operate more than 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions.  Follow FirstEnergy on Twitter @FirstEnergyCorp or online at www.firstenergycorp.com

 

SOURCE FirstEnergy Corp.


These press releases may also interest you

at 10:00
As First Nations and Métis communities are increasingly at the forefront of Ontario's energy transformation, the Independent Electricity System Operator (IESO) is providing up to $15 million for Indigenous energy planning, infrastructure development...

at 09:47
TotalEnergies Marketing USA, a leading provider of high-performance lubricants and specialty fluids, today announced a strategic partnership with OK Petroleum, a well-respected distributor in Long Island, NY. This collaboration will bring...

at 09:15
Argent Trust Company, as Trustee of the Cross Timbers Royalty Trust (the "Trust") , today declared a cash distribution to the holders of its units of beneficial interest of $0.135867 per unit, payable on May 14, 2024, to unitholders of record on...

at 09:15
Argent Trust Company, as Trustee of the Hugoton Royalty Trust (the "Trust") announced today there would not be a cash distribution to the holders of its units of beneficial interest for April 2024 due to the excess cost positions on all three of the...

at 09:15
Argent Trust Company, as the trustee (the "Trustee") of the San Juan Basin Royalty Trust (the "Trust") , today declared a monthly cash distribution to the holders (the "Unit Holders") of its units of beneficial interest (the "Units") of $1,065,685.42...

at 09:00
Yinson Production Offshore Pte. Ltd. ("Yinson Production") is pleased to announce the successful placement of a USD 500 million senior secured bond issue with a 5-year tenor and a fixed coupon of 9.625% per annum in the Nordic bond market. This bond...



News published on and distributed by: